| Task | DCS | Developer workload estimate (person months) |
|---|---|---|
| 80 DR fixes | 16 | |
| Test 3 headed Linux configuration | 2 | |
| WWA WarnGen VTEC QC (RWP 288) | 2494 (decoder)
2495 (IGC) 2496 (text WS) |
3 |
| eliminate localization endian dependency
(localization will be run on Linux box) |
2497 | <1 |
| RedHat 7.2 | 2498 | <1 |
| High density winds | 2499 | 4 |
ORPG items [only those with a DCS # made the cut]:
|
2503 |
TBD |
We installed RH7.2 on ws6-fsld and loaded OB2 on fsld on 7 Nov. We also put 7.2 on all fslt boxes on the 7th, though fslt is still running OB1. Except for WarnGen-related work, internal check-in deadline was 18 Nov, with hand-off to NWS 6 Dec.
Other NGIT/NWS schedule dates include:
| Milestone | Date |
|---|---|
| GFS handoff | 16 Dec |
| IRR0 | 23 Dec |
| IRR1 | 6 Jan 03 |
| Start Pre-SwIT | 6 Jan |
| End Pre-SwIT | 7 Mar |
| IRR2 | 7 Mar |
| Start SwIT | 10 Mar |
| End SwIT | 25 Apr |
| IPR1 | 25 Apr |
| Start SIT | 28 Apr |
| Start Alpha Test | 5 May |
| End Alpha Test | 25 May |
| Start Beta Test | 2 Jun |
| End SIT | 6 Jun |
| IPR2 | 6 Jun |
| Start SyAT Dry Run | 9 Jun |
| End SyAT Dry Run | 13 Jun |
| TRR | 13 Jun |
| Start SyAT | 16 Jun |
| End SyAT | 20 Jun |
| End Beta Test | 25 Jun |
| SVR | 21 Jul |
| Start general field deployment | 23 Jul |