Details of some requirements still to come...
Based on the schedule dated 7 May 03...
Design approach reviews were to be completed by 25 Apr (though in fact
the VCP DAR was completed 27 May). The check-in deadline (PVCS code
check-in) for OB3 is 26 Jun, except for QuikSCAT, which is delayed to
early August due to late delivery of data from NESDIS.
Other NGIT/NWS schedule dates include:
| Milestone | Date | |
|---|---|---|
| GFS handoff | 30 Jun | done |
| IRR0 | 8 Jul | |
| IRR1 | 14 Jul | |
| Start pre-SwIT | 14 Jul | |
| SMM handoff | 29 Aug | |
| End pre-SwIT | 12 Sep | |
| Start SwIT | 15 Sep | |
| UM handoff | 26 Sep | |
| End SwIT | 31 Oct | |
| IPR1 | 3 Nov | |
| Start SIT | 3 Nov | |
| Start Alpha Test | 10 Nov | |
| End Alpha Test | 28 Nov | |
| Start Beta Test | 8 Dec | |
| End SIT | 12 Dec | |
| IPR2 | 15 Dec | |
| Start SyAT Dry Run | 15 Dec | |
| End SyAT Dry Run | 19 Dec | |
| TRR | 3 Feb 04 | |
| Start SyAT | 4 Feb | |
| End SyAT | 10 Feb | |
| End Beta Test | 11 Feb | |
| SVR | 20 Feb | |
| Start general field deployment | 26 Feb |