Based on the revised schedule [PDF] dated 19 May 04...
Important Deadlines:
| SMM Handoff | 27 Feb 04 |
| UM Handoff | 26 March |
| Last DR checkin before SIT (WFOA) | 2 April |
| Training Material Handoff | 23 April |
| Last DR checkin before Beta release | 14 June |
| Last Beta Fix Checkin | 23 August |
Other NGIT/NWS schedule dates include:
| Milestone | Date |
|---|---|
| GFS handoff | 22 Dec |
| IRR0 | 5 Jan 04 |
| IRR1 | 12 Jan |
| Start pre-SwIT | 12 Jan |
| SMM handoff | 27 Feb |
| End pre-SwIT | 5 Mar |
| IRR2 | 8 Mar |
| Start SwIT | 8 Mar |
| UM handoff | 26 Mar |
| End SwIT | 16 Apr |
| IPR1 | 19 Apr |
| Start SIT | 19 Apr |
| Start Alpha Test | 26 Apr
Update: 28 Apr at NHDA; 5 May BCQ |
| End Alpha Test | 2 Jul |
| End SIT | 2 Jul |
| IPR2 | 2 Jul |
| Start SyAT Dry Run | 6 Jul |
| Start Beta Test | 6 Jul |
| End SyAT Dry Run | 13 Jul |
| TRR | 17 Aug |
| Start SyAT | |
| End SyAT | |
| End Beta Test | |
| SVR | |
| Start general field deployment |