| Task | DCS |
|---|---|
| D2D tasks | |
| Dual-pol (OSIP 05-023, continued) | 3504 |
| FAA radar data (OSIP 06-077) | 3505 |
| Various DRs; OB9.2 | |
| GFE tasks | |
| GFE Identifiers at NHC (OSIP 07-047) | 3513 |
| Various DRs; OB9.2 | |
| Integration Handoff Checklists: | OB9 |
The tasks are extracted from the OB9 task list (29 Apr; xls).
There are no hardware architecture changes planned for OB9. Plans for OB9.2 include an upgrade to RHEL5.
OB9.1 is an OS upgrade, to RHEL5. OB9.2 and 9.3 are mainteance releases, with less formal testing than the major release. Blank fields indicate "NA". Original dates were based on the OB9 Release Schedule v2.2, 16 Oct 07 [PDF], and updated from the 9 Jan 08 OB9 kickoff meeting presentation [PPT]. Latest revisions based on OB9 Release Schedule v8, 16 Sep 08 [PDF] and events since.
Note: OB9.3 has been canceled due to development pressures for AWIPS II.
| Milestone | OB9 Date | OB9.1 Date | OB9.2 Date | OB9.3 Date |
|---|---|---|---|---|
| finalize COTS/freeware list | 15 Jan 08 | |||
| requirements reviews | Jan/Feb | |||
| Design reviews | Feb/Mar | |||
| Interface reviews | Apr | |||
| Test plan reviews | Apr/May | |||
| Draft IHC documentation | 20 May | |||
| Code check-in for PIT | 20 May | |||
| functional testing | 27 May - 13 Jun | |||
| PIT with forecasters | 17 - 19 Jun | |||
| Integration handoff checklists due | 20 Jun | |||
| Integration handoff reviews | 23 - 27 Jun | |||
| Integration handoff | 30 Jun | |||
| Code check-in for SwIT | 1 Jul | 12 May 09 | ||
| Build test environment | 2 - 3 Jul | |||
| Final fixes for PIT | 8 Jul | |||
| Pre-SwIT | 7 - 18 Jul | |||
| SwIT | 21 Jul - 29 Aug | May - 17 Jul | 24 Aug - 9 Oct | |
| Check-in for SWiT/α critical DRs | 7 Oct | |||
| SIT | 2 Sep - 10 Oct | |||
| Alpha Test | 2 Sep - 10 Oct | |||
| Beta Test | 13 Oct - 30 Jan 09 | 20 Jul - 14 Aug | 12 - 23 Oct | |
| Release Notes, UM | 2 Sep (α), 14 Oct (β), 2 Feb |
|||
| SMM | 20 Oct (β), 30 Jan | |||
| Last post-Beta checkin | 16 Dec | |||
| SyAT | 12 - 16 Jan | |||
| SVR | 30 Jan | 18 Aug | 29 Oct | |
| Field deployment | 11 Feb - 12 Jun | 31 Aug ff. | 9 Nov ff. |